AquaGeo Groundwater Consulting have completed the the management of drilling of production, injection and groundwater monitoring bores for the construction phase of Iluka’s Cataby Project.
They have worked for 350 days on site from November 2017-October 2018 with no LTI’s or MTI’s and drilled 33 dewatering wells, 20 monitoring wells and 3 reinjection bores across the site.
Celebratory BBQ with AquaGeo and AusDrill Northwest Pty Ltd on completion of the project
Comments